1 Design of project is presented by
A A drawings
B rates
C B.O.Q
D M.B
2 Details not shown in the drawing is presented by
D A drawings
B rates
C B.O.Q
D specifications
3 Rough cost estimate is carried out to get
B A budget
B administrative approval
C technical sanction
D project report
4 Specifications are essential part of
B A contract
B tender
C estimate
D all of these
5 Name nature and class of work is described in specifications
A A general
B detailed
C standard
D all of these
6 Quality and method of execution of work is described in the
specifications
B A general
B detailed
C standard
D all of these
7 The quantity of water will be require for 50 kg cement in
concrete (1:2:4)
C A 20 liter
B 25 liter
C 30 liter
D 33 liter
8 The description for an item of work while preparing detailed
estimate.
C A general specification
B nomenclature
C both a & b
D none of these
9 Thickness of D.P.C is kept
C A 3”
B 1.5”
C 1”
D 2.5”
10 The specifications required to prepare detailed estimate
C A detailed
B general
C both a & b
D none of these
11 Area accupied by walls is _______ in the plinth area
A A included
B excluded
C a or b
D a and b
12 For circular or polygonal shaped building with symmetrical
section of wall this method of estimating is most suitable
A A center line
B crossing
C supliment
d out to out in to in
13 To get length of a step of straight wall. The difference of
widths of that step and of step at superstructure is _________ in the original
length
B A subtracted
B added
C a or b
D a and b
14 Half width is subtracted at each end of middle wall in _______
method of estimating
A A centre line
B crossing
C supliment
D out to out in to in
15 Length of each step remains constant in the case of
perpendicular wall of ______ shaped wall.
D A H
B E
C F
D b and c
16 Such gradients are given in the roads in hilly area
B A flat
B steep
C inverse
D double
17 The transverse slope of the road is called
B A gradient
B side slope
C camber
D super elevation
18 If product of depth at centre line and cross slope increases the
half breadth of a hilly road then section of this road will be in
A A fully cutting
B fully filling
C cutting and filling
D any one
19 If bed level of a canal is lower than natural surface level
where as full supply level is above it then this section will be called
C A fully cutting
B fully filling
C cutting and filling
D any one
20 The method for quantity of earth work in which quantity is less
C A mean area method
B mid area method
C co-ordinate method
D none
of these
21 For earth work unit of measurement is
C A m
B m2
C m3
D Km
22 Transverse slope / cross slope of road appearing in
cross-section is called
B A gradient
B camber
C cross slope
D country slope
23 Longitudinal slope of a road is called
A A gradient
B camber
C cross slope
D country slope
24 A table showing quantity of materials required for a particular
work is called
C A estimate
B analysis of rates
C material statement
D all of these
25 The measuring unit of premixed carpet is
B A Cft
B Sq.m
C R.ft
D M
26 Land width of arterial road is
C A 110 ft
B 115 ft
C 120 ft
D 125 ft
27 Overall cost of any item of work is determined per unit quantity
of work by
B A estimate
B analysis of rates
C quotation
D tender
28 The volume of one bag of cement in M.K.S system is to be
D A 0.25 cum
B 0.025 cum
C 0.35 cum
D 0.035 cum
29 Dry quantity of cement is always more than its wet quantity by
D A 1.27
B 1.37
C 1.44
D 1.54
30 Overall cost of any item of work is determined per unit quantity
of work by contractors profit in estimate is added in the following rate
D A market
B analysed of rates
C scheduled
D all of these
31 Mostly thickness of cement plastering is kept
ANS A 1 / 2” or 12 mm
32 Increasing factor is directly proportional to _________ in the
ingredients of concrete or mortar
C A weight
B volume
C voids
D all of these
33 In first class brick work volume of dry mortar is taken as of
total brick work
C A 15 %
B 25%
C 30 %
D 50 %
34 The quantity of cement (in bags) will be required for 100 sft.
Flush pointing with cement mortar (1:3)
A A 0.53 bags
B 1.53 bags
C 2 bags
D 2.53 bags
35 No. of bricks will be required for 1 cum dry brick masonry
A A 500
B 510
C 550
D 610
36 A table showing quantity of materials required for a particular
work is called
A A material statement
B estimate
C analysis of rates
D all of these
37 Which are the overhead charges in rate analysis
D A furniture
B salaries
C office rent
D all of these
38 Manhole constructed to join two sewer line at different levels
is called
C A large manhole
B shallow manhole
C deep manhole
D lamp hole
39 Sewer lines laid in the streets joining main or branch sewer
line at the road are called
C A trunk sewer
B domestic sewer
C lateral sewer
D main sewer
40 Indicating size of sewer pipe denotes its __________ diameter
A A internal
B external
C mean
D anyone
41 The measuring units of refilling of trench for sewer line will
be
D A Ft
B Rft
C Sft
D Cft
42 An amount which has to be set aside at fixed intervals of time
out of the gross income to accumulate to initial cost of the property is called
D A gross rent
B net rent
C depreciation
D sinking fund
43 The loss in the value of a property due to its use wear and tear
and decay etc is called
C A gross rent
B net rent
C depreciation
D sinking fund
44 The decrease in value of property due to un-preferred style
C A depreciation
B declination
C obsolescence
D none of these
45 Method of determining depreciation in which it is assumed that
property looses its value by a constant amount every year is called
A A straight line
B constant percentage
C sinking fund
D quantity surveyor
46 The value of fixed percentage of depreciation (rd) after 50
years of a building will be
B A 1.5
B 2.00
C 2.5
D 3.00