1 A triangular shape side
wall of a slopping roof is called
A A gable
B gambrel
C truss
D toe
2 Top most joint of a truss is called
B A heel
B ridge
C cleat
D pitch
3 Amount of maximum steel reinforcement in RCC structures is
B A 6
%
b 8%
c 10%
d 12 %
4 In case of angle of inclination of ________ vertical and
horizontal sizes of column base are equal.
B A 30o
B 45o
C 60o
D 75o
5 Minimum nominal mix of concrete used with steel reinforcement
D A 1:1:2
B 1:1.5:3
C 1:2:4
D 1:3:6
6 Trusses are used to support load of roofs for _____ span
A A longer
B shorter
C both a & b
D none of these
7 A rafter of a truss which directly receives the load of roof
is called
B A principal
b common
c gable
d purline
8 Outer support of truss which receives the load of sloping roof
is called
A A principal
rafter
B purlins
C common rafter
D none of these
9 For longer span of sloping roof the most suitable supporting
member is
A A truss
B T – beam
C doubly reinforced beam
D none of these
10 ________ Is the horizontal member used to support common rafter
of truss.
B A panel
B purlin
C gambel
D eave
11 Walls constructed below floor level of bridge and across the
flow of water are termed as
D A toe
wall
B pier
C abutment
D wing wall
12 A water tank constructed below ground level is called.
A A underground
water tank
B overhead water tank
C surface water tank
D all of these
13 End supports of bridge which are constructed parallel to flow of
water
A A abutments
B piers
C wing wall
D toe wall
14 Middle support of bridge constructed to flow of water.
B A abutments
B piers
C wing wall
D toe wall
15 T-beam and slab type bridges are suitable upto_________ span.
A A 20
m
B 25 m
C 30 m
D 35 m
16 Triangular shape of pier end at up stream side is called.
C A round
nose
B ease water
C cut water
D none of these
17 Overhead reservoir is also called.
B A high
level reservoir
B elevated tank
C Both a & b
D none of these
18 Capacity of water tank should meet ________ hour demand of
population.
A A 6
B 8
C 10
D 12
19 A pipe at the bottom to empty the water tank.
D A blind
pipe
B vent pipe
C over flow pipe
D washout pipe
20 A pipe provided at maximum water level in a water storage tank to
flow on exceeding the capacity of tank is called
A A vent
pipe
B washout pipe
C overflow pipe
D all of these
21 Method of execution of work in which time limit is not mentioned
is called
A A piece work agreement
B contract
C work order
D tender
22 A contract in which measurement and payments to the contractor
are made on item wise is called.
A A lump
sum contract
B item rate contract
C cost plus fixed fee
23 _____ Is item of water supply
D A bib
cock
B union
C urinal
D all of these
24 Measuring unit of gas fitting
B A m2
B R-m
C No
D none of these
25 The permeable formation
of the soil of the earth’s crust is called
A A aquifer
B aquiclude
C aquifuge
D none of above
26 Measuring unit of sinking well.
C A Sft
B Cft
C Rft
D none of these
27 _____ Is the process of digging well with the help of well kerb.
A A sinking
B excavation
C blasting
D all of these
28 In eagle point following type of setting is carried out for
selecting units
D A main
toll bars
B primary setting
C secondary setting
D prototype setting
29 Smallest unit in a project.
B A WBS
B activity
C event
D node
30 In eagle point software project setting contains
D A units
B format
C precision
D all of these
31 Relationship between activities of a project in primavera.
D A start
to start
B start to finish
C finish to start
D all of these
32 Relationship between activities of a project in primavera.
D A start
to start
B start to finish
C finish to start
D all of these
0 Comments