1 ______ is a managerial function which decides what when where
and how of a job
A A planning
B organizing
C staffing
D controlling
2 A form of human association for achieving a common goal.
A A organization
B construction team
C project team
D staff
3 The concept of functional organization was developed by
B A henri
fayol
B F.W taylor
C H.L gantt
D P.F drucker
4 In irrigation department a circle is headed by
C A SDO
B exam
C SE
D chief engineer
5 In _____ organization experts of every field are available
B A line
B functional
C line & staff
D staff
6 Technical sanction of
project is given on the basis of
B A rough cost estimate
B detailed estimate
C revised estimate
D anyone
7 Feasibility report
includes
D A preliminary survey
B rough
cost estimate
C site selection
D all of these
8 Estimate required to
get technical sanction is
B A rough
cost
B detailed
C revised
D none of these
9 The purpose of ________ report is to see that project is
beneficial from economic & social point of view
C A project
B progress
C feasibility
D all of these
10 Probable time of completion of project can be ascertained from
A A preliminary
planning
B feasibility report
C project report
D rough cost estimate
11 Detailed drawings are to be included in ________ report
B A feasibility
B project
C progress
D all of these
12 Preparation program of construction systematically is called
A A scheduling
B planning
C execution
D tendering
13 Arrangement of storing for construction material on a prescribed
from is known as ___ schedule.
D A construction
B labour
C finance
D material
14 Earliest method used for planning of projects
C A CPM
B pert
C bar chart
D milestone chart
15 Owning cost of machinery is called
C A cost
+ fuel
B cost + repair
C cost of purchase
D none of these
16 Earth moving machinery having swinging blade at its middle
D A tractor
B bulldozer
C ripper
D scraper
17 Operational cost of machinery ________
B A cost
of purchase
B fuel
C repair
D all of these
18 Carrying out construction work according to specification is
called
A A quality
control
B inspection
C execution
D progress
19 Before inspection ________ should be decided
C A specification
B time of inspection
C degree of accuracy
D all of these
20 Method of execution of work in which time limit is not mentioned
is called
A A piece
work agreement
B contract
C work order
D tender
21 ____ Contract deals with ready made articles or services
B A lump
sum
B turnkey
C package
D labor
22 In _______ contract payment is made for all items of work
together.
C A item
rate
B turnkey
C package
D cost plus fee
23 No construction work can be started until land is
A A acquired
B leased
C pledged
D purchased
24 _______ Is the invitation of rates from contractors for
construction of work or supply of material
B a tender
B quotation
C bid
D all of these
25 _______ Is the offer to supply some material or construction of
work on contract
A A tender
B quotation
C grant
D contract
26 Tenders called from one or two contractors
B A private
tender
B negotiated tender
C open tender
D none of these
27 Tender is not acceptable without submitting _______ with it.
C A security
money
B demand notes
C earnest money
D all of these
28 Is the approval by competent authority for execution of project
B A administrative
approval
B technical sanction
C both a & b
D none of these
29 Earnest money is kept a percentage of total cost of project
A A 2
%
B 5 %
C 10%
D 20 %
30 Retention money is usually ________ % of the total cost of work
B A 5
B 10
C 15
D 20
31 Advance payment made to the contractor for making necessary
arrangement to start work is called.
B A secured
advance
B mobilization money
C retention money
D earnest money
32 Unpaid wages of work people engaged on the work is recorded in
this part of muster roll
B A 1st
B 2nd
C 3 rd
D 4th
33 A bill payment is called
A A voucher
B indent
C both a & b
D none of these
34 _____ Is authorized to draw money from treasury on bills for
making payments
C A SDO
B XEN
C DDO
D site incharge
35 Advance payment made to contractor against security of material
at site
C A first
payment
B imprest
C secure advance
D security
36 Overall control of stores lies with an officer called
C A sub
engineer
B SDO
C XEN
D S.E
37 Store debitable to _______ account are used to record material
purchased for unidentified projects.
A A suspense
B final
C major
D minor
38 _________ Head of account is used for material purchased for
identified project
B A suspense
B final
C major
D minor
39 A triplicate from used to issue some articles from store is
called
A A indent
B quotation
C tender
D M.B
40 ________ Is the counting of stock after suitable intervals.
A A physical
verification
B inspection
C recounting
D all of these
41 _________ Account of material is maintained at site of project
C A suspense
B detailed
C material at site
D none of these
0 Comments